We are happy to announce that the construction has started at Camera Park! Over the next few months excavation and demolition will take place to prepare the area for new amenities. New amenities include a state of the art ADA accessible playground, a splash pad, fitness station, challenge course, disc golf and new restrooms. This project is partially funded by an OSLAD grant and will be completed by the end of the year.
Please keep in mind that during construction, certain areas of the park may be affected. We appreciate your patience and look forward to the grand re-opening of Camera Park!
May 17:
The old playground equipment has been removed.
June 1:
The remainder of the old playground has been removed and the base of the inclusive playground has started to be installed.
The disc golf baskets have been installed.
July 2:
The inclusive playground equipment has been installed.
Overview look of the current construction.
August 18:
The foundation of the splash pad has been installed.
September 24:
More landscaping work and the colored base for the playground has been installed.
October 11:
The surface of the splash pad has been installed, along with the concrete sidewalk along the playground. The foundation for the splash pad mechanical room has been laid.
December 14:
Construction on the pump house and new restrooms continue. The removal of the old storage and concession building has begun.
View of the construction area looking north. The inclusive playground and splash pad are complete, along with much of the landscaping as construction moves northward to continue construction with the pump house and restrooms. You can see the challenge course has begun to be installed with the southern half directly to the right of the splash pad. Once the old storage and concession building has been completely removed, the northern half of the challenge course will be completed, along with the installation of fitness equipment to the north of it.
May 11:
Construction on the splash pad pump house is almost complete, just waiting on some electrical work!
Construction of the Challenge Course is complete! The new fitness equipment has been installed and can be seen in the background.